Road Closure from 7th August 2017

Wiltshire Council has made an Order to close temporarily to all traffic:

C391 Bradford Road (Part), Winsley; from its junction with Dane Rise to a point approximately 100m east of Tyning Road.

To enable: Wales and West Utilities to carry out gas mains replacement and connection work.

Alternative route: via C391 Bradford Road / Limpley Stoke Road (unaffected length) – B3108 Winsley Bypass – C391 Winsley Road / Bradford Road (unaffected length) and vice versa.

The closure and diversion route will be clearly indicated by traffic signs.

This Order which previously came into operation on 10 April 2017 will now recommence on 7 August 2017 and it is anticipated that the closure will be required until 1 September 2017. It is anticipated that the works will take the stated duration to complete depending upon weather conditions. Access will be maintained for residents and businesses, although delays are likely due to the nature of the works. The Order has a maximum duration of 18 months.

BRADFORD ROAD, WINSLEY
ROAD CLOSURE & TRANSPORT PLAN
7th – 28th August 2017

Phase 1 – Monday 7th August to Sunday 13th August
2/3 way traffic lights and working from the Bradford side roundabout to the junction of Tyning Road (junction of Tyning Road to be kept clear for buses to sweep)
265 Bus: normal routes with slight delays due to traffic lights.

Phase 2 – Monday 14th August to Sunday 20th August (this may be extended to possibly 23rd August) Tyning Road Junction with Bradford Road closed for larger vehicles due to inability to sweep clear of the works
265 Bus: All buses to use bypass – no buses to serve within the “Old Village”, Seven Stars or Dorothy House due to blocked junction at Tyning Road. 2 Temporary Bus Stops will be established – to the West of Dane Rise and also Late Broads.

Phase 3 – Monday 21st August to Monday 28th August (Bank holiday)
Dane Rise to junction of Tyning Road – closed (junction of Tyning Road to be kept clear for buses to sweep)
265 Bus: All buses to pass Cottles Lane / Ashley Lane / Tyning Road / By Pass and vice versa – no buses in “Old Village”, Seven Stars or Dorothy House. A Temporary Bus Stop will be established by Cottles Lane / Ashley Lane plus the Temporary Bus Stops for Phase 2 will continue to operate.

Relevant information will be displayed on all bus stops.

This information can also be downloaded here.

Links:
Closure Notice
Plan