Works to redevelop Avonpark Retirement Village are underway. The works include the redevelopment of facilities at the site and an expansion in the accommodation provided.
The works are scheduled to take place throughout 2026 and 2027, with an estimated completion date of Summer 2028.
A temporary compound for construction vehicles has been made at the end of the ‘dog walking’ field, with access maintained to the ‘football field’ on the far side (near to the bypass).
During the works there will be times when the main drive is out of use for limited periods. Vehicles needing to access Avonpark will be diverted via Quarry Close. Avonpark will keep in touch with affected residents and information will be put out to the Winsley community via the Community Website and Facebook page.
The slides below outline the schedule of works to be undertaken.