A36 and B3108 roadworks update – October 2024
National Highways has provided the following update on the temporary re-opening of the A36:
The A36 will temporarily re-open from approximately 8.00pm on Friday, 18th October to allow Wiltshire Council to carry out essential work on the A350. It will then stay open over the half term break and close again on the evening of Sunday 10th November at approximately 9.00pm. National Highways may still be working in the area during this time.
Due to the damage to the southern embankment, there will be two-way traffic lights in place to keep everyone safe. However, the road will be open to all traffic, but not pedestrians, the footpath will remain closed.
The traffic management arrangements will return exactly as they are currently from the 10th November. The closure of the southbound entrance to Lower Stoke and the ANPR camera will be in place from 7.00am on Monday 11th November.
Details can be found on the National Highways project webpage:
Additionally, please see the information below about some closures of the B3108 at the Limpley Stoke railway bridge:
Network Rail will be undertaking work on the railway bridge at Limpley Stoke, which will require the shutting of the B3108 at the bottom of Winsley Hill on the following days:
Monday 21 October to the morning of Friday 25 October (4 nights), evening closure from 9pm to 6am.
Saturday 26 October closed continuously for 36 hours until midnight on Sunday 27 October (Monday 28 October morning).
Saturday 2 November evening closure from 10pm to 6am.
Saturday 9 November evening closure from 10pm to 6am.
Arrangements for the D1 bus: During the evening closures and Sunday, most D1 buses will be looping via Winsley as they have previously done albeit these vehicles may operate a little late. On Saturday only, from 2.00pm to 6.30pm, due to general higher traffic, we have agreed with FirstBus to operate a shuttle bus between Bradford on Avon and Winsley (and return).
Unfortunately, these arrangements will mean that Winsley Hill (Avon Park), Limpley Stoke, Viaduct and Claverton will not have a bus during the closure periods.